Project Preparation:
Task |
Expected End Date |
Status |
Select name |
2009/June/25 |
Done |
Create CPM |
2009/June/30 |
Done |
Register project in SourceForg |
2009/July/01 |
Done |
Create a Wiki |
2009/July/01 |
Done |
Create Project web page |
2009/July/1 |
Done |
Create Project Plan |
2009/July/01 |
Done |
Create Project Schedule Page |
2009/July/01 |
Done |
Learning Git |
2009/July/06 |
Done |
Milestone 1:
Task |
Expected End Date |
Status |
Understanding XML Light |
2009/July/08 |
Done |
Design |
2009/July/09 |
Done |
Make improvements in XML Generator |
2009/July/11 |
Done |
Perform a release |
2009/July/11 |
Done |
Milestone 2:
Task |
Expected End Date |
Status |
Change HTML data structures to use XML Light |
2009/July/14 |
Done |
Develop Menu converter |
2009/July/17 |
Done |
Perform a release |
2009/July/18 |
Done |
Milestone 3:
Task |
Expected End Date |
Status |
VXML output tags converter |
2009/July/20 |
Done |
Forms and fields tags converter |
2009/July/24 |
Done |
Grammar converter |
2009/July/30 |
Done |
Main program |
2009/August/03 |
Done |
Perform a release |
2009/August/05 |
Done |
Milestone 4: ( Extra, if we have time)
Task |
Expected End Date |
Status |
Understanding Tree dot module in Haskell |
2009/August/05 |
Done |
Design Tree visualizer |
2009/August/06 |
Done |
Develop the tree visualizer |
2009/August/11 |
Done |
Perform a release |
2009/August/12 |
Done |
Testing and Integration |
2009/August/13 |
Done |